Relevant Events

Relevant Events

So, what is a relevant event and why do you need to know?

To start with the relevant events we are discussing today are only relevant to a JCT form of contract and are set out within the contract and can often be added too, removed or amended within a schedule of amendments or within an order.


So, a relevant event is an event on or off site that can cause a delay to the completion date of the works and is identified within the contract as a relevant event, 

 

Section 2.26.14 of the JCT 2016 D&B gives one such example that we are all probably familiar with “Force Majeure” or Covid 19 for people that may not know.

 

“Ok so what does that mean to me?” I hear you ask. Well, this leads on from Section 2.24 Notice by the contractor of delay to progress .1 if and whenever it becomes reasonably apparent that the progress of the works or any section is being delayed the contractor shall forthwith give notice to the employer of the material circumstances, including the cause or causes of the delay, and shall identify in the notice any event which in his opinion is a relevant event.

This then leads onto section 2.25 fixing completion date .1 if on receiving a notice and particulars under the clause 2.24: .1 and of the events which are stated to be a cause of delay is a relevant event, and .2 completion of the works or of a section is likely to be delayed thereby beyond the relevant completion date, then save where these conditions expressly provide otherwise, the employer shall give an extension of time by fixing such later date as the completion date for the works or section as he then estimates to be fair and reasonable.

 

Ok so that will have confused some out there so let us simplify it. The list of relevant events in the contract are events outside of the contractor’s control. If one of these events effects the progress of work onsite causing a delay to the end date, then as long as you have notified them in line with the contract, they have no grounds to refuse an extension of time. Its particularly important to point out that employers can and do amend these clauses a lot so its very important to know your contract and know how to administer it correctly.

  • #contracts
  • #planning
  • #delayanalysis
  • #projectmanagement

We provide planning solutions for builders, contractors, fit out contractors and larger sub contractors. We produce construction programmes, progress reporting and monitoring. Re-programming and all…

Follow us for more articles and posts direct from professionals on      
  Report
Property

Understanding the Importance and Types of Emergency...

Why Do We Need Emergency Lighting? Emergency lighting plays a critical role in ensuring life safety first in any…
Employment & HR

Labour’s new Employment Rights Bill: challenges employers...

The introduction of Labour’s Employment Rights Bill on 10th October 2024 has created a significant shift in how…

More Articles

Business Management

The Value of a Sustainability Strategy in the Tender Process

In today’s competitive landscape, businesses face increasing pressure to demonstrate their commitment to…
Business Management

Unlocking the Power of Raw Financial Data

At Master of Coin Consulting, we offer independent strategic finance advice to help micro to medium-sized businesses…

Would you like to promote an article ?

Post articles and opinions on Professionals UK to attract new clients and referrals. Feature in newsletters.
Join for free today and upload your articles for new contacts to read and enquire further.